How long does a restaurant buildout take?

From signed lease to first service, a typical DMV restaurant takes six to twelve months. That spread isn't randomness — it's a handful of decisions and a few known bottlenecks. Here's the schedule as it actually runs, phase by phase.

The phases

  • Concept and design (4–10 weeks): space planning, kitchen design, and construction documents. Health-department requirements shape this from day one.
  • Permitting (4–16 weeks, parallel): building permit review, health plan review, and — if applicable — liquor licensing all running concurrently.
  • Procurement (parallel): kitchen equipment, hoods, and walk-ins ordered as soon as drawings are set; long-lead items order before permits land.
  • Construction (10–20 weeks): demolition, rough-in, inspections, finishes, and equipment set. A second-gen conversion sits at the short end; full shell buildouts at the long end.
  • Inspections and opening (2–5 weeks): final trade inspections, health pre-operational inspection, Certificate of Occupancy, staff training, and soft opening.

The four delays that actually happen

  • Long-lead equipment: custom hoods, walk-ins, and imported equipment can run 8–16 weeks — ordered late, they idle a finished kitchen.
  • Utility upgrades: new gas or electrical service involves the utility's timeline, not yours — discovered mid-project, it's a multi-month hole.
  • Permit comment cycles: every round of reviewer comments costs 2–6 weeks; slow responses multiply it.
  • Landlord approvals: work-letter sign-offs, building engineer reviews, and after-hours rules quietly add weeks in occupied buildings.

How the fast projects do it

Fast projects aren't rushed — they're parallel. A contractor engaged at lease signing walks the space, flags utility and infrastructure gaps while the architect draws, orders long-lead equipment as drawings are set, and submits health review alongside the building permit. The construction itself rarely differs between a fast project and a slow one; the calendar difference is almost all in the overlap.